Electricity generation on Nigeria’s national grid has dropped to about 3,180 megawatts (MW), leaving distribution companies with a combined allocation of 2,885MW and raising concerns over deteriorating power supply across the country.
Data obtained by The Guardian showed that grid generation stood at 3,743MW around midnight yesterday and declined to 3,732MW by 2 a.m. It later fell sharply to 3,179MW at 6 a.m.
The figures were recorded despite about 21 electricity generation companies operating on the national grid, highlighting the persistent challenges facing Nigeria’s power generation and distribution network.
Data from the Distribution Load Profile published by the Nigerian Independent System Operator (NISO) on November 18, 2026, at 6:28 p.m. showed that the 11 electricity distribution companies received a combined allocation of 2,885MW.
Abuja Electricity Distribution Company (AEDC) received the highest allocation of 551MW, followed by Ikeja with 366MW, Ibadan with 340MW and Eko with 339MW.
Port Harcourt received 279MW, followed by Benin with 230MW, Enugu with 220MW, Kano with 173MW, Kaduna with 167MW and Jos with 146MW. Yola recorded the lowest allocation at 74MW.
The generation shortfall comes amid concerns among power sector stakeholders over inadequate water reserves for hydroelectric plants, gas supply constraints, transmission infrastructure failures and regulatory penalties imposed on generation companies.
Although NISO recently attributed the decline to gas supply challenges, a source at a generation company told The Guardian that the system operator could not claim to be unaware of the difficulties confronting the generation segment. The source argued that the issues affecting output had been discussed at a stakeholder meeting involving NISO, the Nigerian Electricity Regulatory Commission (NERC) and generation companies (GenCos).