First Niger Bridge To Reopen Next Week, Says Umahi

‎The Federal Government says the First Niger Bridge will reopen to traffic next week, following the completion of key rehabilitation works on the bridge linking Anambra and Delta States.

‎

‎Minister of Works, David Umahi, gave the assurance on Wednesday after inspecting the ongoing repairs at the Onitsha Bridge Head.

‎

‎The bridge was closed earlier this month after the discovery that vandals had removed critical structural components, including bolts, nuts and portions of the expansion-joint steelwork.

‎

‎The closure, which was initially expected to end on September 21, was extended by one week following persistent rainfall.

‎

‎Umahi said the contractor, SKECC, had made significant progress, noting that the vandalised bolts had been replaced and properly secured.

‎

‎He also disclosed that the specialised expansion joint removed by vandals had been manufactured and brought into the country for installation.

‎

‎While acknowledging the progress achieved within about 10 days, the minister stressed that safety would remain the priority before the bridge is reopened.

‎

‎“We are not going to be stampeded to open the bridge until the major structural work has been achieved,” Umahi said.

‎

‎He directed the contractor to undertake additional works, including repainting the bridge’s structural components, caps and internal carriageway sections, as well as removing illegal advertisements from the facility.

‎

‎The minister also ordered the installation of additional solar-powered streetlights and the completion of CCTV cameras, with the surveillance system to be linked to the Second Niger Bridge.

‎

‎Umahi further directed an empirical assessment of the bridge’s structural elements, both above and below the water level, to establish their condition.

‎

‎He said the assessment report must be submitted before the current phase of rehabilitation is concluded.

‎

‎On the bridge approaches, the minister ordered a review of the proposed asphalt works, directing that concrete be used on sections that are expected to undergo reconstruction in the future.

‎

‎According to him, the approach would prevent public funds from being wasted on asphalt that could subsequently be removed during reconstruction.

‎

‎He added that one carriageway could be opened once the concrete attains the required strength, while rehabilitation continues on the other side.

‎

‎Meanwhile, Delta State Commissioner for Works, Rural Roads and Public Information, Charles Aniagwu, commended the Federal Government for the speed and quality of the rehabilitation.

‎

‎Aniagwu recalled that Umahi had inspected the bridge on August 28 and directed the replacement of the vandalised bolts, nuts and expansion-joint components.

‎

‎He said the directives had been implemented, while damaged portions of the asphalt surface had also been removed and replaced.

‎

‎“We are pleased with the speed of work. We also appreciate our people who demonstrated a whole lot of patience to understand that you are after their safety,” Aniagwu said.

‎

‎The commissioner added that the rehabilitation had substantially improved the condition of the bridge and expressed confidence in the durability of the work.

‎

‎He said the cooperation of motorists and other road users had also helped to facilitate the rehabilitation process.

‎

Related posts

2027: ADC will be on ballot, Atiku, David Mark faction candidates may not – Keyamo‎

Uba Sani donates vehicles to JNI, CAN, religious sects

El Niño: Nigerian govt knows danger, yet no light – Utomi blasts Tinubu over blackout